The feasibility study for the Duyun to Shangri-La National Expressway (Guizhou Section), specifically the Duyun to Anshun segment, has passed the review.


Entrusted by the Ministry of Transport (Department of Comprehensive Planning), China Communications First Highway Exploration and Design Institute Co., Ltd. has formed an expert panel to... 2016 Year 4 At the beginning of the month, we conducted on-site surveys and reviews of the feasibility study project for the Guizhou section of the Duyun-Shangri-La National Expressway, which our company has completed—the Duyun-Anshun segment.

The research team listened to the report from the Guizhou Provincial Development and Reform Commission on submitting... G7611 A request for the Feasibility Study Report on the Duyun to Shangri-La Expressway, Duyun to Anshun Section, and the National Expressway. G7611 An introduction to the “Feasibility Study Report for the Duyun-Shangri-La Expressway, Duyun-Anshun Section” (hereinafter referred to as the “Report”), during which key project sites—including the Wuyang, Yunwu, Huishui, Dalong, Yangjiashan, and Laomianhe Super Bridges—were inspected on-site. Project documentation was reviewed, and the review panel concluded that the content and depth of the “Report” submitted by our company meet the requirements of the current “Measures for Preparing Feasibility Study Reports for Highway Construction Projects” issued by the Ministry, and thus approved the report in principle.

According to the feasibility study report, the total length of the recommended route for the proposed project is: 284.741 kilometers, of which the main line is long 219.027 Kilometers, Duyun branch line length 42.269 Kilometers, the Gui'an branch line is long. 23.445 Kilometers—the National Highway Network Plan ( 2013 Year~ 2030 Year)》Xia Rong National Expressway (G76) The connecting line is also the Duyun-Shangri-La Expressway. (G7611) The first section is an integral part of Guizhou Province’s expressway network. It plays a crucial role in perfecting the national expressway network layout, deepening the implementation of the Western Development Strategy, and effectively carrying out the State Council’s policies. [2012]2 The document is of great significance for accelerating the development of the Gui'an New Area.

In the next phase of work, our Planning and Consulting Institute will further refine the feasibility study report based on the comments and suggestions provided by the expert panel, and promptly submit supplementary reports and relevant documents.

 

 

(Yang Jing)   Liu Changchun)


  • File size: 200